Part 1: Exercises

5. Calculate early start, early finish, late start, late finish, and float for each of the activities in the network below. The duration of each activity is given.

A diagram of a block diagram  Description automatically generated

6. Identify the critical path for the network in Exercise 5. How long should the project take?

9. Given the information below, create the project schedule network. Then, using the enumeration method, calculate and show all of the paths through the network. Show how long each path will take. Identify the critical path. Show the schedule on a Gantt chart showing critical and noncritical activities and float.

A table of a chart  Description automatically generated with medium confidence

Part 2 Scheduling Problem

Complete the following:

Your child is a school theater group member and has been asked to prepare the schedule, etc. for a skit to be performed during the 4th of July celebration in the local village square.  As a volunteer, you offer to serve as the project controller because of your expertise in schedule management.

1. Construct an AON diagram similar to the format used in the Youtube videos found in the commentary using an MS Excel spreadsheet.  Ensure that you include a Start activity and a Finish activity.  Include a legend.

Make a diagram using the example below

AON" Diagram on sheets - from data ?! : r/sheets

2. Calculate the estimated time for each activity using PERT techniques for the 3 estimates provided.  Include a sample calculation.

3. Prepare a table that identifies all paths and their lengths.  Which path is the critical path?

4. During the execution phase of the skit project, one of the activities on the critical path is delayed by one day.  Is this serious?

5. Using the activity estimates for optimistic, pessimistic and most likely time to complete activities on the critical path, qualitatively discuss the estimate uncertainty of the critical path.

 

 

 

Activity  

Predecessor

 

Time (days)

     

Optimistic

 

Most Likely

 

Pessimistic

1 None 2 4 6
2 None 5 5 5
3 2 3 5 7
4 1 7 10 13
5 1 11 12 13
6 2,4 5 6 7
7 3 9 10 11
8 3,6 5 7 9
9 4 7 9 11
10 5 3 3 3
11 7 15 17 19
12 8 6 8 10
13 9,10 7 8 15
14 7 12 14 16
15 12,13 16 17 18
Looking for a solution written from scratch with No plagiarism and No AI?

WHY CHOOSE US?

We deliver quality original papers

Our experts write quality original papers using academic databases.We dont use AI in our work. We refund your money if AI is detected  

Free revisions

We offer our clients multiple free revisions just to ensure you get what you want.

Discounted prices

All our prices are discounted which makes it affordable to you. Use code FIRST15 to get your discount

100% originality

We deliver papers that are written from scratch to deliver 100% originality. Our papers are free from plagiarism and NO similarity.We have ZERO TOLERANCE TO USE OF AI

On-time delivery

We will deliver your paper on time even on short notice or  short deadline, overnight essay or even an urgent essay